On Time and Under Budget
 
 
         
 

Designing better learning enviroments...

 

          Averaged Construction Cost 10% Below Budget
         

 

Innovative Design has a solid reputation for bringing in its schools on time and under budget. Despite the extensive energy and environmentally sound measures incorporated into our schools, we have averaged construction costs 10% below budget.

North Carolina Schools  
Budget
Cost
Four Oaks Elementary School 1991
$ 6,748,625
$ 6,542,138
Clayton Middle School 1993
$ 7,800,000
$ 7,831,197
Selma Middle School* 1993
$ 6,500,000
$ 7,045,000
Durant Road Middle School 1995
$15,983,526
$12,330,986
Sterling Montessori Academy 1996
$ 1,500,000
$ 1,500,000
East Clayton Elementary School 1997
$ 9,120,000
$ 8,785,000
Dillard Road Middle School 1998
$14,873,000
$12,588,949
The New School 1999
$ 1,744,260
$ 1,400,000
Smith Middle School 2001
$13,450,000
$12,688,000
Millbrook Elementary School 2002
$6,400,000
$ 5,794,000
Heritage Middle School** 2004
$17,429,000
$14,647,000
* Additional classrooms were added during construction
**Bid Price

 

Smith Middle School in Chapel Hill, NC, incorporates extensive daylighting, a 2.6 million gallon per year rainwater catchment system, a solar hot water system for the cafeteria, a two kilowatt roof-integrated photovoltaic system which converts sunlight to electricity, and numerous green products, and was three-quarters of a million dollars under budget.